Budapest Metro revamp: 3 new stations to be completed by May
The renovation of the most popular Budapest metro line, the M3, is to reach a new cornerstone by May. The capital’s public transport company, BKV Zrt, announced that they would open three renewed underground stations by the end of spring.
Magyar Építők, a Hungarian construction news outlet regularly reports about the revamp of Budapest’s most used underground line, the M3. More people use this underground on a workday than the entire Hungarian railway system. Therefore, the BKV Zrt renews it segment by segment to avoid public transport chaos.
The SWIETELSKY Építő Kft. takes care of the last, third segment of the work between the Lehel and Nagyvárad Squares, while another company of this group, the Swietelsky Vasúttechnika Kft., is responsible for the renovation of the railway lines and the relevant technology.
The BKV Zrt. announced on the project’s official website that they were about to finish the work at the Kálvin Square, Corvin District and Semmelweis Clinics Stations soon. All of the three renewed metro stations have been equipped with so-called sloping lifts to help the disabled to use the underground. Three more stations will have such services: Ferenciek Square, Arany János Street and Nyugati Railway Station.
It will be the first time in Hungary that passengers can use this service. The sloping elevators will run in the escalator shaft, right next to the stairs, Zoltán Kurucz, the designer said. He highlighted that the elevator would accommodate eight people or a wheelchaired person and his attendant at a time. Furthermore, it would move at the same speed as the escalator.
According to the designer, the operation of the sloping track elevator is “almost 100 percent identical” to that of the Budavár cable car. To this day, only Stockholm and New York have such slopes in the metro. Interestingly, Swedish, Greek and French experts are also participating in the construction of the new Budapest metro stations, added Zoltán Kurucz – pestubuda.hu reported before.
The three M3 stations are nearly completed but operational tests are still taking place. For example, constructors test the new smoke and heat extraction systems.
During the smoke tests, they try to model a possible fire emergency. They aim to create a system guaranteeing passengers to reach the exits before they start suffocating due to the smoke.
Authorities have already approved the system at the Semmelweis Clinics and Corvin Stations. Magyar Épitők says that they would soon test the Kálvin Square Station, as well.
Read alsoMetro line M3 in Budapest may stop because of the war
Source: Magyar Építők, pestbuda.hu
please make a donation here
Hot news
Top Hungary news: snow covered Hungary, regime change in Budapest parking, forint free fall – 22 November, 2024
THE ranking: Győr’s Széchenyi István University among the top science universities
Hungarian minister proud that both German and Chinese battery plants are built in Hungary
Here are the top Hungarian cities for expats seeking a new home
Drugs situation in Budapest serious, leading politician says
“Hungarian Iron Dome” deployed near the Ukrainian border, expert says Putin will attack Hungary
3 Comments
This renovation of m3 is such a bad joke, they had all the time in the world to work on it. How many stadiuma were built from zero during this renovation?
Nice, modernised stations but will there be any trains? That rubbish Russian rolling stock is not fit for purpose.
Forward thinking , by those in Governmental Authority, in the planing of the renovations of the M3 “Second Stage” – included, additional requirements, in the event, Budapest, Hungary found it-self “embroiled” in the conflict of war being witnessed between the Ukraine and Russia.
Must applaud this present Government its FOCUS – on us the Citizens of Hungary – FIRST, and not whats in it for them /.
We TRUST – the Government, has not commenced, the renovation – up-grade of the Rakosi Bunker / F4 Object – which STILL exists – and be – Reborn for “those” in favour of the Government at the time – to take logings approx 2500 people.