• Coronavirus in Hungary
  • Budapest
  • Hungary border control
  • HelloMagyar
EnglishFrenchGermanSpanish
EnglishFrenchGermanSpanish
Government: Metro 4 case ‘textbook example of fraud’Government: Metro 4 case ‘textbook example of fraud’Government: Metro 4 case ‘textbook example of fraud’Government: Metro 4 case ‘textbook example of fraud’
  • Politics
  • Business
  • Society
  • Sport
  • Culture
  • Special Hungary
  • News To Go
  • World
  • Contact Us
  • About us
  • About us
  • Contact Us
  • Privacy Policy
✕
Breaking News
  • NATO will kick out Hungary for sacking ‘NATO friend officers’ from the Hungarian military?

Support us
Daily News Daily News · 12/02/2017
· Politics

Government: Metro 4 case ‘textbook example of fraud’

corruption European Anti-Fraud Office's (OLAF) Metro 4 fraud

Budapest, February 12 (MTI) – The report by the European Union’s anti-fraud office OLAF identifying corruption surrounding Hungary’s metro 4 construction project shows that the handling of the project was a “textbook example of fraud”, government office chief János Lázár said.

Speaking to public Kossuth Radio in a pre-recorded interview broadcast on Sunday, Lázár said the total cost of the metro project was 430-450 billion forints (EUR 1.4-1.5bn), of which 380 billion had been paid out.

The project is still in its closing phase, as the capital is still receiving government support for it, he said.

The government is due to transfer the final 20 billion forints to Budapest this year, but that transfer is being suspended, Lázár said. Given that criminal activities are suspected in connection with the project, under Hungary’s budget law, the government cannot spend taxpayer money on it until the OLAF investigation of the case is closed and it becomes clear who is legally responsible for what had happened, Lázár said.

He noted that the Prime Minister’s Office has launched an investigation to determine whether the alleged misappropriations also concerned government money contributed to the project.

“It appears that they did,” Lázár said, citing the OLAF report which he said indicated that the “frauds” suspected in the case involved not just the misappropriation of European Union funds but also funds transferred directly from state coffers.

If the suspected irregularities are confirmed, Budapest will have to be asked to repay the misappropriated funds to the government, Lazar said.

He said that “in simple terms” what had happened was that international corporations involved in the project “such as Siemens or Alstom” had “joined forces” with the municipal council leadership at the time, the various technical supervisors and designers and “robbed Brussels and the Hungarian budget”.

He said the reason why the current municipal council leadership was now in “a difficult position due to [former liberal Budapest mayor] Gábor Demszky’s activities” was because the EU was expected to demand that Hungary pay back the misappropriated funds and the Hungarian state can do so as well.

He said the EU would not wait for the case to be wrapped up in the Hungarian justice system before issuing its reimbursement demands, adding that this would have serious financial bearing on the capital.

Lázár added, at the same time, that Prime Minister Viktor Orbán had instructed members of the government to provide any assistance they can to the capital in resolving the matter.

On another subject, Lázár praised Hungary’s management of its EU funds, declaring the country the “winner” of the 2014-2020 funding cycle. He said the government would call tenders for all EU funds available for the current funding period by March 31. Of the 9,000 billion forints available, 2,200-2,700 billion forints will be spent on development projects, he said. The government aims to disburse all of the available funds by March 31, 2018, he added.

Source: MTI

corruption European Anti-Fraud Office's (OLAF) Metro 4 fraud
Share
Daily News
Daily News

2 Comments

  1. Anonymous says:
    12/02/2017 at 22:23

    In this period i was teaching one of the heads of the bidding teams. That person went to the meetin gat which Alstom was awarded the contract. The three final bideers were given an envelope (yes it was in wrting) which included the details of where the extra money should go if they were awarded the contarct. All the bank account were outside of Hungary and the value was about 20% of the final price. If no one can send taroudn 20- poepl to jail then they shoudl take a gun to tehri head and shoot themmselves. The info id easily available but allaprties are involved.

  2. Romulus X says:
    15/02/2017 at 13:04

    I reckon much more than 20% lost in fraud
    Line 4 is 10 stations and 7.4 km for 1.4 -1.5bn Euros
    Bucharest M6 is equivalent , all underground, 17km and 12 stations, and our budget is 1.0bn Euros.
    maybe it will run out to 1.1bn Euros, but Budapest is about 75% overpriced, at least.

Leave a Reply

Your email address will not be published. Required fields are marked *

SUPPORT US

Subscribe to our newsletter

Sign up to receive daily updates, news & stories about Hungary!

Select your location below or enter your country so we can deliver our morning newsletters to you in time.


Thank you!

You have successfully joined our subscriber list.


.

Latest news
  • PHOTOS: Esztergom-Budapest has new auxiliary bishop
  • What happened today in Hungary? – 4 February, 2023
  • ASTONISHING VIDEO of the renewed castle of the ‘Greatest Hungarian’, Count Széchenyi
  • VIDEO, PHOTOS: Brutal windstorm in Hungary, buildings collapsed, trees uprooted, traffic disastrous
  • Debrecen’s new battery plant will have brutal high water consumption?
  • MEP Gyöngyösi: The EU must support Ukraine in guaranteeing minority rights
  • Want to learn Hungarian? Here are the best apps!
  • What will the Russians say? Hungarian military to start drills in Tallinn next week

About us

Contact us

Copyright rules

© 2023 DailyNewsHungary. All rights reserved! | Server and development by Svigelj Levente E.V