The arrival of a melt trap indicates “another milestone” in the country’s nuclear plant upgrade now under way at Paks, in southern Hungary, the foreign minister said on Thursday.
The massive, new equipment, 15 metres high, 11 metres in diameter and weighing over 730 tonnes, was produced in Russia, Péter Szijjártó said, adding that it would be placed directly below the reactor to catch spilt liquid in an emergency.
The minister said the production process in Russia had been monitored by Hungarian experts and representatives of the Hungarian Atomic Energy Office “to ensure that the best and most secure equipment is completed”.
The Hungarian side approved the melt trap’s completion on March 29, he said, but noted that shipping had taken a long time. “An Austrian company organised shipping, that took 42 days … shipping across the Black Sea and along the River Danube involved reloading the melt trap and its accessories several times,” Szijjártó said.
He said construction was going ahead “full steam” with 900 people working at the site, but added that at peak times of the project the headcount could reach 8,000-10,000 people. He said 21,000 posts out of a planned 76,000 to stabilise the soil had been sunk, while the soil under the new fifth block was 86 percent complete.
Read also:
please make a donation here
Hot news
Top Hungary news: winter is here, Romania joins Schengen, American woman’s murder details – 23 November, 2024
Hungarian foreign minister outrages for US sanctions against Putin’s Gazprombank
Suleiman the Magnificent: The Great Sultan’s heart rediscovered in Hungary
The National Bank of Hungary cooperates with Chinese university
PHOTOS: Beloved Hungarian hotel in the picturesque Danube Bend reopens in five months
Attention, users! BudapestGO app renews in November, new features available
1 Comment
The Real Person!
The Real Person!
Hungary should say thank you. Russia seems to come across in all its agreement. Better than EU that changes rules faster than the weather changes.