The Hungarian government initially granted state aid for the construction of two new reactor blocks at the Paks II nuclear power plant. While the European Commission approved the funding in 2017, Austria appealed the decision. Now, the European Court of Justice has ruled differently, potentially restarting the full review process and casting doubt over the viability of the contract with the Russian contractor. According to the government, the court’s decision will not cause any delays, and construction work is soon set to begin.

What troubles have beset Paks II?

The Paks II project, undertaken with Russian financing and a Russian contractor under an intergovernmental agreement, last made headlines earlier this year when independent MP Ákos Hadházy claimed the Russian firm was laying off large numbers of employees. Just days later, the project again attracted attention when the Paks II site experienced a shift in the retaining wall of one of its foundation pits. While Rosatom was reportedly unaware of the incident, the German contractor remained silent.

Now the project is back in the spotlight after the Luxembourg-based European Court of Justice overturned the European Commission’s 2017 decision, which had concluded that Hungary’s state aid was proportionate, limited in scope, and minimally distortive to competition, granted for the construction of two VVER-1200 reactor units.

Paks II nuclear project US
Photo: Facebook / Paks II. Atomerőmű Zrt.

Russian contractor awarded project without open bidding

The construction was awarded without a public procurement process to the Russian company Nizhny Novgorod Engineering (NNE). While the European Commission originally approved this, Austria filed a lawsuit in 2018 challenging the decision. According to Portfolio, Austria argued that the direct awarding of the contract violated EU procurement rules, and the Commission had erred in granting approval. Portfolio reports no new Austrian evidence, suggesting none was submitted in the case.

At the end of the proceedings, the Court annulled a previous decision by the General Court of the European Union, which had found that Hungary acted lawfully in providing state aid for Paks II.

Csárdi visit Paks Hungarian Atomic Energy Authority
Photo: FB/Paks II NPP Ltd

What was the Court’s issue?

The European Court found that the Commission had failed to fully assess whether the direct, competition-free contract with the Russian NNE was compliant with EU procurement laws. The Court argued that a competitive bidding process might have resulted in a cheaper project.

Continue reading

2 Comments

  1. We know the E.U. does absolutely nothing that benefits the native European peoples, but does it HAVE to actively work AGAINST them!?!?!?

  2. Good for the EU. Pity they can’t kick Hungary out, they’d obviously like it better in the Russian Federation LMAO.

    Oh, and Michael Whiner Steiner, you’re welcome to go too 🐷🤣

Leave a Reply

Your email address will not be published. Required fields are marked *